Analysis of Management Reserve and Schedule Slip in a Steel Truss Bridge Project
How to cite (AJARCDE) :
Project implementation delays (schedule slips) not only affect project completion time but may also influence the adequacy of the project’s cost reserve (management reserve). This study aims to analyze the relationship between schedule slip and management reserve using the Earned Value Analysis (EVA) approach through the Estimate at Completion (EAC) and Variance at Completion (VAC) parameters. The study utilized planned S-curves, weekly progress reports, and the project contract value as the Budget at Completion (BAC) from a steel truss bridge construction project with a planned duration of 35 weeks and an actual completion time of 36 weeks. EVA parameters were evaluated at each reporting period. The Actual Cost of Work Performed (ACWP) was determined using the Project Implementation Budget (Rencana Anggaran Pelaksanaan/RAP) approach at 90% of the contract value, while the management reserve was established at 10% of the BAC. The results demonstrate that schedule slip is directly associated with an increase in the EAC value, leading to a reduction in the VAC value toward the management reserve threshold. Conversely, improvements in schedule performance increased the VAC value above the management reserve limit, indicating that the project’s cost reserve remained secure. Although the project experienced a one-week delay at completion, the VAC value remained within the management reserve threshold, confirming that the management reserve was still adequate. These findings indicate that project delays significantly affect the dynamics of management reserve conditions through changes in the estimated final project cost.
Contribution to Sustainable Development Goals (SDGs):
SDG 9: Industry, Innovation and Infrastructure
SDG 8: Decent Work and Economic Growth
SDG 11: Sustainable Cities and Communities
[1] M. C. Winoto, K. Guwinarto, and S. Limanto, “Faktor Penyebab dan Dampak Keterlambatan Pelaksanaan Proyek Konstruksi Menurut Kontraktor Terhadap Indikator Performa Proyek,” Jurnal Dimensi Pratama Teknik Sipil, vol. 1, no. 12, pp. 56–63, 2023, Accessed: Jan. 15, 2026. [Online]. Available: https://publication.petra.ac.id/index.php/teknik-sipil/article/view/13435/0
[2] A. Sujarwo and W. Oetomo, “Analisis Waktu dan Biaya Pembangunan Gedung IKFM, IPS, IPL Dan Parkir Kendaraan Karyawan,” Jurnal Keilmuan Teknik Sipil, vol. 5, no. 1, pp. 269–278, Jun. 2022, doi: 10.31602/jk.v5i1.7527.
[3] Jamal and M. R. Ian, “Analisis Faktor Penyebab Keterlambatan Proyek Konstruksi di Indonesia,” Jurnal Kajian Teknik Sipil, vol. 10, no. 1, pp. 1–8, 2025, doi: 10.52447/jkts.v10i1.8071.
[4] A. E. Susanto and H. Wiyanto, “Analisis Pengaruh Keterlambatan Proyek Terhadap Estimasi Biaya dan Waktu Penyelesaian Proyek X di Sawangan,” JMTS: Jurnal Mitra Teknik Sipil, vol. 8, no. 1, p. 51, 2025, doi: 10.24912/jmts.v8i1.32613.
[5] Z. R. Kamandang, I. N. D. P. Putra, and A. R. Nauli, “A Guideline of Earned Value Method (EVM) Implementation as Decision Baseline on Acceleration Solutions for Construction Project Scheduling,” in The Innovation Breakthrough in Digital and Disruptive Era, Manado: Technium: Romanian Journal of Applied Sciences and Technology, Oct. 2023, pp. 447–453. doi: 10.47577/technium.v16i.10027.
[6] E. D. Widowati, “Komparasi Prediksi Penyelesaian Proyek dengan Earned Value dan Earned Schedule,” Akselerasi?: Jurnal Ilmiah Teknik Sipil, vol. 7, no. 2, Nov. 2025, doi: 10.37058/aks.v7i2.16407.
[7] W. D. Rachman, S. Utoyo, and S. Safiatus Riskijah, “Evaluasi Kinerja Waktu dan Biaya pada Proyek Gedung X Menggunakan Metode Earned Value Analysis,” Jurnal Online Skripsi Manajemen Rekayasa Konstruksi, vol. 5, no. 3, pp. 22–27, Sep. 2024, doi: 10.33795/jos-mrk.v5i3.4430.
[8] E. Yonamastuti, I. A. Asri, H. P. Adi, and E. M. Satrio, “Evaluasi Kinerja Biaya dan Waktu dengan Metode Earned Value (Studi Kasus Ruko di Jalan Ki Ageng Panjawi, Kecamatan Klaten Utara, Kabupaten Klaten),” Jurnal Ilmiah Sultan Agung, vol. 3, no. 1, pp. 16–26, Mar. 2024, Accessed: Jan. 16, 2026. [Online]. Available: https://jurnal.unissula.ac.id/index.php/JIMU/article/view/36946
[9] S. Hariyadi, H. T. Tjendani, and B. Witjaksana, “Cost and Time Analysis Using the Earned Value Analysis Method,” Eduvest - Journal of Universal Studies, vol. 3, no. 9, pp. 8273–8283, Sep. 2024, doi: 10.59188/eduvest.v4i9.6402.
[10] M. Trianshy, A. F. Edriani, and S. Bahri, “Analisis Faktor Cost Overrun Dan Time Overrun Pada Proyek Konstruksi Di Kota Bengkulu,” Jurnal Multimedia Dehasen, vol. 1, no. 2, pp. 27–36, Apr. 2022, doi: 10.37676/mude.v1i2.2063.
[11] R. Susanti and A. Nurdiana, “Cost Overrun in Construction Projects in Indonesia,” in IOP Conference Series: Earth and Environmental Science, Institute of Physics Publishing, Jun. 2020. doi: 10.1088/1755-1315/506/1/012039.
[12] Project Management Institute, Practice Standard for Earned Value Management. Pennsylvania: Project Management Institute, Inc, 2005. [Online]. Available: https://www.pmi.org/standards/earned-value-management

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.